Stand alone operations are ongoing for Thales and KhSC. While Thales performs electrical and mechanical Spacecraft checkouts in H103A, KhSC works in H101 to prepare for operations on the Breeze-M which arrived at Yubileiny and was transported by truck to 92A-50 on 4 Mar. The Launch vehicle is finishing pneumatic testing and after cleaning and testing, the payload fairing halves are resting in storage until integration. RUAG specialists are scheduled to arrive within the week to begin work on the separation system. Coordination meetings between the teams are increasing in frequency and duration which means the Spacecraft and payload adaptor fitcheck is just on the horizon.